Weekly Construction Update, 3-20-17

  • 14 March 2017

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator
970-390-4677 or 970-479-2198; lsandoval@vailgov.com

Upcoming Activities

April 3     I-70 Vail Underpass Construction Resumes
April 11   Weekly Construction Meetings Begin
April 12   Town of Vail Annual Construction Kickoff
April 23   Vail Mountain Closes
April 24   One-way detours on frontage roads begins, re: underpass construction
April 24   Spring Bus Service begins with West Vail Adjustments
April 27   Free Workshop on Sustainable Landscaping
May 6     Annual Highway Cleanup
May 12   Hard to Recycle Collection
May 13   Town of Vail Cleanup Day

I-70 Vail Underpass Major Construction Starts Up April 3

The I-70 Vail Underpass Project will soon be entering the fourth and final phase of construction. Crews will mobilize on site in mid-March for minor work beneath the underpass, with major construction activities resuming Monday, April 3, involving occasional lane closures on I-70 and minor frontage road delays. The one-way detours return to the frontage roads on Monday, April 24; impacts to drivers will be no different than what occurred in 2016. Remaining activities include extensive construction of the underpass roundabouts, as well as construction beneath the underpass, including brick pavers, curb and gutters, and lighting elements. In addition, crews will do final restoration work in 2017. The project is scheduled for completion in fall of 2017. For updated project information, visit www.codot.gov/projects/i70vailunderpass, or call the project hotline at 970-685-7706. To help commuters plan their drives and to follow progress of the construction, a webcam has been installed. Visit the project website or go to www.vailgov.com/webcams/i70 to view.

Free Landscape Workshop on April 27 to Focus on Best Practices

 Registration is now taking place for a free workshop on sustainable landscaping practices scheduled for Thursday, April 27 in Vail. This free, day-long workshop will take place from 8:30 a.m. to 4 p.m. in the Grand View on the third level of the Lionshead Welcome Center. Sponsored by the Town of Vail, Eagle River Water and Sanitation District and Betty Ford Alpine Gardens, this is the second year for the training and coincides with expanded educational programming identified in the Town of Vail Gore Creek Strategic Action Plan. Landscape contractors, commercial applicators, designers, architects and property managers are encouraged to register in advance to attend. Lunch will be provided as well as free parking. To RSVP,  contact Peter Wadden, the town’s watershed education coordinator, at pwadden@vailgov.com, by Monday, April 24.

New Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at vailgov.com.


Here’s a recap of the various construction projects in and around Vail.

Vail Village

Red Lion Inn Condo # 3 Renovation, 304 Bridge Street
This project is schedule to start on April 25 with a completion date of spring of 2018. A crane is required which will necessitate a closure of Bridge Street. These dates have yet to be determined. Contractor will notify all merchants and properties in the area prior to any closure. Work consists of adding 714 square feet to level 1 and level 2 of the unit. Contractor is Beck Building Company, Kevin Fifield, 970-904-1283. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Vail Valley Medical Center Phase 1: West Wing, 181 West Meadow Dr.
Construction on the project continues with work contained within the construction fence. This project consists of a new fourth floor and expansions on the south and west sides. All hospital services will remain open and fully functional throughout the construction. To access the Emergency Department, use West Meadow Drive. All other patients and visitors should access the hospital via South Frontage Road West. Phase I is scheduled to be completed in 2017. Contractor is G.E. Johnson Construction Company, Christian Earl, 307-203-9242. VVMC Construction Team contacts are Mike Pritchard, 970-471-9367 and Mark Lehman, 970-471-9662. Town of Vail contact is Leonard Sandoval, 970-390-4677.

303 Gore Creek Drive, Units 11 & 12
This is an Interior remodel and addition. Completion date is currently scheduled for spring of 2018. Contractor is SRE Building Associates, Justin Marschalk, 970 376-2944. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Lionshead Village

The Lion Redevelopment (formerly Strata and Lionshead Inn and Lionshead Annex), 705 W. Lionshead Circle
The Lion has received its Temporary Certificate of Occupancy (TCO). Landscaping and other remaining improvements will be completed in the spring of 2017. Contractor is PCL Construction, Inc. Town of Vail contact is Leonard Sandoval, 970-479-2198.

Outlying

Donovan Park Restroom Repairs
Update: Work has been completed following plumbing repairs and restrooms are now open. Town of Vail contact is John King, 970-479-2170.

Donovan Park Picnic Shelter
Construction of a new picnic shelter for Donovan Park continues. Work is contained within a 6-foot high construction fence between the playground and the basketball court. Walkways will continue to be open. The new structure will accommodate three picnic tables and will be completed by the spring of 2017. The contractor is R.A. Nelson. Town of Vail project manager is Gregg Barrie, 970-479-2337.

Booth Creek Park redevelopment, 2900 Manns Ranch Road
Construction of the Booth Creek Park redevelopment project continues but is on hold for the winter months. Site work and building construction is almost complete. The construction fence has been moved to encompass the playground area only. Park visitors are welcome to walk through the park but the paths will not be maintained in the winter. The parking spaces on Manns Ranch Road will no longer be plowed.  Completion of the playground and landscaping work will occur as soon as the weather and site conditions allow in the spring. The work involves a compete redevelopment of the existing park and includes new hard-surface tennis courts, picnic pavilion, restrooms and children’s playground. The park is anticipated to be completed in November 2016. Town of Vail contact is Todd Oppenheimer at 970-479-2161.

Hotel Talisa (formerly Vail Cascade Resort and Spa) Renovation, 1300 Westhaven Dr.
This $50 million renovation project includes upgrades to guest rooms, restaurant, market, lounge and bar area, new spa and more. The Aria Athletic Club and Spa and Vail Cascade Condominiums will remain open throughout the construction, which is scheduled to be completed in spring of 2017. General Contractors is PWI Construction working on the hotel improvements; Evans Chaffee Construction Group will work on the tennis court conversion. Black Line Group, Todd Goulding, 970-331-1732, is the project manager. Town of Vail contact is Leonard Sandoval, 970-479-2198.

Doubletree Hotel, 2211 North Frontage Road (formally the Holiday Inn)
Work includes renovation of the interior/exterior of the hotel, pool area upgrades and parking lot improvements. Start date was Aug. 15, 2016; completion date scheduled for spring 2017.  Contractor is Peak Professional Contractors Inc. Contact person, Valerie Thodde, owner’s rep/ project manager, 954-675-1522.


Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for the email updates, visit Vailgov.com and click on “Town Services,” then “Vail Mail Newsletter.” On this page you can sign up for “Construction Updates” as well as other useful Town of Vail newsletters.

 