Weekly Construction Update, 6-25-18

  • 24 June 2018

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator
970-390-4677 or 970-479-2198; lsandoval@vailgov.com

Weekly Construction Update Meetings

Weekly contractor construction update meetings are taking place at 9 a.m. on Tuesdays in the Lionshead Welcome Center. Meetings will be held every Tuesday through the fall of 2018. The public is invited to attend.

Upcoming Holidays and Special Events – Construction Restrictions

Vail Farmers’ Market – Sundays, June 17-Oct. 7
Vail America Days™– July 2-8

Numerous Construction Projects Taking Place on behalf of Town of Vail

Ten town-sponsored maintenance and construction projects are underway this season with additional projects taking place later in the year. The activities include numerous street and park maintenance commitments, water quality improvements and construction of a new parking structure. In all, the projects represent nearly $24 million in budgeted public improvements extending from West Vail to East Vail. Project descriptions are included below.

Online Citizen Portal

Customers of the Community Development Department have access to a 24/7 online citizen portal to submit applications for contractor registration and various construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning and Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vailgov.com/online-services.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at www.vailgov.com.


Here’s a recap of the various construction projects currently ongoing in Vail as well as projects that will be beginning soon.

Vail Village

2018 Vail Asphalt Overlay Project
The Town of Vail has contracted with Elam Construction to complete this year’s asphalt overlay project. This year’s project includes asphalt milling and paving on roads in Vail Village and the Golf Course neighborhood. Single lane traffic will be maintained during the work. Elam will return in a few weeks to mill and pave the scheduled Golf Course roads. Project contacts are Erik Schmidt with Elam Construction, 970-926-5411, and Chad Salli, Town of Vail, 970-376-2389.

Slifer Square Repair Project/Covered Bridge
The spring construction phase is complete. The next phase will resume on Sept. 4. The Town of Vail has contracted with Icon Inc., of Gypsum to complete the Slifer Square Repair Project. Slifer Square, located between the Vail Village parking structure and the Covered Bridge, is undergoing necessary repair projects. During construction, the in-town bus will be rerouted onto the frontage road and pedestrian traffic will be routed around the construction to the covered bridge to maintain access to businesses in Vail Village. Work is scheduled for the spring and fall Village construction seasons. Final completion date is Nov. 15.  Project contacts are Albert Quintana with Icon Inc., 970-977-0561, and Chad Salli, Town of Vail, 970-376-2389.

Vail Transit Bus Stop Improvements at Vail Village and Lionshead Transit Centers
The Village transit stop is nearly complete with landscaping work remaining. Work will continue in the Lionshead transit area into early July. The Town of Vail is adding two new bus stops at the Vail Village and Lionshead transit centers. The Vail Village Transit Center bus stop will add capacity with the construction of two new bus bays along the South Frontage Road in front of the Vail Village parking structure. The Lionshead Transit Center bus stop will add capacity with a new westbound stop in front of the Lionshead parking structure entry along the South Frontage Road. In addition, landscape improvements will be installed at the Lionshead structure in conjunction with the bus stop work. Contractor is Kramer North America; Town of Vail project contact is Tom Kassmel, 970-479-2235.

Ski and Snowboard Club Vail Redevelopment, 598 Vail Valley Drive
Driveway and paver walkway improvements continue, which require a sidewalk closure on Vail Valley Drive. Vail Valley Drive will be narrowed to a single lane during working and non-working hours. Traffic control will be provided. Construction activity is contained within the construction fenced area. This is a redevelopment of the Ski and Snowboard Vail site to include a private and public club and multi-family residential dwelling units. The bike path on the south side of the project is closed until the project is complete. Vail Valley Drive will see an increase in oversize vehicle construction traffic. Completion date is early winter 2018. General contractor is Viele and Company, David Viele, 970-476-3082. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Hill Building, 254 Bridge Street
Construction deliveries will continue to occur on Bridge Street for the project between 7 and 8:30 a.m. Oversize deliveries for the project on Upper Bridge Street will be coned off to keep pedestrians safe while material is delivered. Pedestrian traffic control will be provided. This is a major remodel of the building. Use of Bridge Street is allowed Monday through Saturday, April 16-June 22. Use of additional right-of-way requires submittal and approval of a public way permit. The trash dumpster will be staged on-site and fenced off. The project completion date is scheduled for fall of 2019. Contractor is Olson & Sons Construction Inc., Tim Olson, 970-390-7303. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Vail Health Hospital East Enabling Work
Demolition of the existing parking structure continues. This includes site shoring in preparation for excavation of the site. All construction traffic will enter and exit on West Meadow Drive, which will see an increase in oversize vehicle traffic. In addition, removal of dirt is currently underway on the north side of the South Frontage Road. Please exercise caution along South Frontage Road and West Meadow Drive near the construction project. Phase II of the Master Facility Plan includes the tear-down and replacement of the current east wing administration building and garage, replacing it with a new garage and new building to house new emergency and imaging departments, as well as a new lobby, central plant, tenant space and material management department. All hospital services will remain open and fully functional throughout the construction. To access the Emergency Department, use West Meadow Drive. Hospital patients and visitors should park in the hospital parking lot on South Frontage Road West. Patients and guests of the Medical Professional Building (US Bank) should park in the lot accessible by West Meadow Drive. Please see map. Contractor is G.E. Johnson Construction Company, Christian Earl, 307-203-9242.Town of Vail contact is Leonard Sandoval, 970-390-4677.

Row House Unit 8, 303 Gore Creek Drive
Work consists of an interior and exterior remodel; work will be contained within property boundaries and construction fencing. Project completion is scheduled for fall of 2018. Contractor is Cuccia Construction, Guy Cuccia, 970-471-6456. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Row House Units 9 & 10, 303 Gore Creek Drive
Single lane closures are scheduled for deliveries and concrete pours throughout the spring and summer months; traffic control will be provided. Construction activity will be contained within property boundaries and construction fencing. Project consists of an interior and exterior remodel. Contractor is Beck Building, Gary Kendall, 720-202-5645. Town of Vail Contact is Leonard Sandoval, 970-390-4677.

Row House Units 11 & 12, 303 Gore Creek Drive
Single lane closures are scheduled for deliveries and concrete pours throughout the spring and summer months; traffic control will be provided, Project consists of an interior/exterior remodel and addition. Project completion date is currently scheduled for spring of 2018. Contractor is SRE Building Associates, Steve Stone, 970-376-3638. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Lionshead

Demo and Restoration of Battle Mountain/Lazier Parking Garage, 534 East Lionshead Cr.
Demolition of existing 2-level parking structure, spanning Lot 1A and Lot 2A. Work includes shoring up west wall and portion of north wall, grading and drainage, and resurface of lower parking surfaces as necessary to maintain drainage and grading, and restore parking with current required dimensions of 9x19. Stairs to be installed at north wall for access between Vantage Point property and lower surface parking. Start date is scheduled for June 11, with a completion date of July 31, 2018. Demo contractor is Spiegel Construction; General contractor is Meadow Mountain Homes, Sean McGinley, 970-926-2824 (office); Town of Vail contact is Leonard Sandoval, 970-390-4677.

Lionsquare Lodge South Interior Renovation, 660 Lionshead Place
All work is currently contained within the site boundaries. The project includes interior upgrades to the existing conference room, including new celling finishes, room dividers, lighting and interior trim. Contractor is R.A. Nelson & Associates Inc., Matt Anderson. Town of Vail Contact is Leonard Sandoval, 970-390-4677.

Vail Marriott Interior Renovation, 715 West Lionshead Circle
The project includes renovation of existing ballrooms, meeting rooms and associated corridors and the renovation of existing guest rooms and corridors. Construction start date was March 26 with a completion date of mid-September. Contractor is Digney York Associates LLC, Don Glorius, 703-790-5281. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Outlying

Red Sandstone Park Maintenance
The playground at Red Sandstone Park will be closed from June 18- 28 to be repainted. Other park facilities including the volleyball court, picnic tables and restroom will remain open. The contractor is Intermountain Painting, John Moore 970-390-7034. The Town of Vail contact is Gregg Barrie, 970-390-3286.

The Valley Condos Parking Lot Improvements, 1490 Buffehr Creek Drive
The Valley Condos has hired Arrow Civil LLC to repair the parking lot retaining walls. Work was scheduled to start on June 12 and has a completion date of July 24. It will required a single lane closure of 12 ft. during daylight working hours and a narrow 18 ft. within the construction area during non working hours. Traffic control will be provided, please exercise caution within the construction area. In addition, due to the construction, residential vehicle parking of 10 vehicles will be relocate to the shoulder of Buffehr Creek Road; the parking locations have been marked. Contractor is Arrow Civil LLC, Todd Burke, 970-274-6486; Town of Vail Contact is Leonard Sandoval, 970-390-4677.

West Vail Sewer Main Improvements – West Vail South Frontage Road
Eagle River Water & Sanitation District, in cooperation with the Town of Vail, is installing new sewer main in two areas within the South Frontage Road West. This project is being completed in two phases; Phase 1 began May 16 and completion has pushed into July. Phase 2 starts June 25 and will take approximately two months. The project is critical to increase sewer main capacity in the West Vail area so ERWSD can accommodate peak sewer flows in the future. Unforeseen subsurface conditions at extreme depths during Phase 1 led to redesign of the downhill portion of the sewer main, thereby extending the duration of the Phase 1 work. The District is partnering with town of Vail to install electrical conduits along South Frontage Road in order to allow for the removal of the existing overhead power lines. The district and town are cooperating to complete both improvements while reducing impacts to the public. Phase 1 of the project takes place between Stephens Park and Elliot Road in one lane of South Frontage Road West. This lane is closed while deep excavation work occurs. Alternating one-way traffic is open in the remaining lane. Flaggers will manage traffic operations during work hours (7 a.m. to 7 p.m.) and automated traffic lights will manage traffic operations at night. Motorists and non-motorists alike must comply with flaggers and traffic lights at all times for their safety due to narrow conditions on the one lane that is open. Phase 2 of the project is located east of the Exit 173 roundabout, on South Frontage Road by the West Vail Conoco. Significant traffic impacts begin June 25. From 7 a.m. to 7 p.m., the eastbound lane of South Frontage Road near Conoco will be closed and the westbound lane will have single-lane alternating traffic. To prevent traffic from backing up into the West Vail roundabout, motorists are advised to use alternate routes – such as the Main Vail exit on I-70  or North Frontage Road to the Sandstone Underpass – to reach the Matterhorn neighborhood and Cascade and Lionshead villages. Both lanes will be open during non-work hours. The bike path is detoured through the construction area and the ECO Transit bus stop has been temporarily relocated a bit east of the regular stop on South Frontage Road. Conoco will remain open and accessible during construction. The contractor is Western Pipeway. ERWSD contact is Jeffrey Schneider, 970-445-7941.

Gore Valley Trail Reconstruction – West Vail South
The Town of Vail is reconstructing approximately 2,700 linear feet of the Gore Valley Trail between Matterhorn Drive (Donovan Park) and the West Vail Conoco. Trail users will be accommodated on the shoulders of the South Frontage Road and West Gore Creek Drive as needed. Project contacts are Roby Forsyth, RPM Construction at 970-471-5584; Town of Vail contact is Gregg Barrie, landscape architect, at 970-479-2337.

Sewer Main Improvements, Bridge Road and Recreation Path in East Vail
The Eagle River Water & Sanitation District, in cooperation with the Town of Vail, is installing new sewer main and manholes along Bridge Road, north of Gore Creek, and along the recreation path west of Bridge Road to near the I-70 East Vail interchange. A recreation path detour is set up near the south side of the East Vail interchange, directing path users to Bighorn Road. A conflict with an unknown buried utility has delayed the project. Active work was suspended while a solution is planned; utility relocations may start this week. Eventually, the Bridge Road bridge will close for one week and access to Bridge Road will be via Lupine Drive. The project should finish in July. Eagle River Water & Sanitation District contact is Melissa Marts, 970-471-1329. Town of Vail contact is Chad Salli, 970-479-2169.

I-70 East Vail Water Quality Improvements
The Town of Vail has contracted with United Companies to install water quality improvements at the East Vail interchange and two additional sites on I-70 near milemarker 182 to treat stormwater runoff.  Work has begun under the I-70 bridges at the end of Bighorn Road and at the East Vail interchange requiring shoulder closures and periodic single lane closures on the North Frontage Road and Bighorn Road. This project is in partnership with the Colorado Department of Transportation which awarded the town a grant to pay for 80 percent of the construction costs. Work will begin the week of May 21 and is scheduled for completion the end of June 2018. Town of Vail contact is Chad Salli, 970-479-2169.

Red Sandstone School Renovation, 551 North Frontage Road
The project includes the complete renovation of Red Sandstone Elementary School. Work includes removing the existing exterior finish material and installing new IECC compliant insulation and new exterior finishes, rearranging the existing school program and classrooms to allow for larger classrooms (to meet the current Eagle County School District standards). The new two story addition along the south façade of the building will create a cafeteria, serving line, and secure vestibule all of which the school does not currently have. The second level of the addition will house the new library expanding the space to transform the library into a media center space as well. Demo and construction is underway, completion is scheduled for mid February, 2019. Contractor is Haselden Construction, Justin Fahnestock, 303-549-8589.
 
Red Sandstone Elementary School Parking Garage, 551 North Frontage Road West
Excavation, shoring and removal of dirt are ongoing. Access to the school and the gymnastics center will be maintained as a clear zone. The bus stop is open west bound only. This project has a completion date of Nov. 15, 2018. The Town of Vail and Eagle County Schools are jointly constructing a four-level, 160 space parking structure on the current Red Sandstone School site. The work will include extensive site work to establish a loop road around the parking structure to allow access to each level while at the same time provide a one-way loop road for school drop-off and pick up. Contractor is Haselden Construction, Justin Fahnestock, 303-549-8589. Town of Vail contact is Chad Salli, 970-479-2169.

Solar Vail Apartments, 501 N. Frontage Road West
The existing employee housing located just east of the Vail Gymnastics Center will be demolished and replaced with a 4-story, 65-unit rental housing development for Sonnenalp Resorts. Asbestos abatement and building demolition will take place in May and June followed by the construction of a cast-in-place underground parking structure and a wood framed building. Occupancy is anticipated by October 2019. Contractor is RA Nelson, Justin Pronga, 970-471-0509. Town of Vail Contact is Leonard Sandoval 970-390-4677.

Chamonix Vail, 2310 Chamonix Road 
The construction of all ten new residential buildings is complete. Each of the new townhomes is now occupied by the new homeowners. All that remains to be completed is the final landscaping. At this time more than 50 percent of the plant materials are installed. The anticipated completion date is prior to June 18.  Once completed, construction activity in the neighborhood will cease. Contact Jason Kiefer, RA Nelson, 970-471-3923 or George Ruther, Town of Vail, 970-376-2675.


Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for the email updates, visit Vailgov.com and click on “Town Services,” then “Vail Mail Newsletter.” On this page you can sign up for “Construction Updates” as well as other useful Town of Vail newsletters.