Weekly Construction Update, Sept. 10

  • 7 September 2018

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator
970-390-4677 or 970-479-2198; lsandoval@vailgov.com

Weekly Construction Update Meetings

Weekly contractor construction update meetings are taking place at 9 a.m. on Tuesdays in the Lionshead Welcome Center. Meetings will be held every Tuesday through the fall of 2018. The public is invited to attend.

Upcoming Special Events – Construction Restrictions

Vail Farmers’ Market – Sundays, June 17-Oct. 7
Octoberfest, Vail Village – September 14 – 16

Online Citizen Portal

Customers of the Community Development Department have access to a 24/7 online citizen portal to submit applications for contractor registration and various construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning and Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vailgov.com/online-services.

Email Notification Service for Contractors and Consultants

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at www.vailgov.com.


Here’s a recap of the various construction projects currently ongoing in Vail as well as projects that will be beginning soon.

Vail Village

Slifer Square Repair Project/Covered Bridge
Phase II will resume on Sept. 4. The Town of Vail has contracted with Icon Inc., of Gypsum to complete the Slifer Square Repair Project. Slifer Square, located between the Vail Village parking structure and the Covered Bridge, is undergoing necessary repair projects. During construction, the in-town bus will be rerouted onto the frontage road and pedestrian traffic will be routed around the construction to the covered bridge to maintain access to businesses in Vail Village. Work is scheduled for the spring and fall Village construction seasons. Final completion date is Nov. 15.  Project contacts are Albert Quintana with Icon Inc., 970-977-0561, and Chad Salli, Town of Vail, 970-376-2389.

Ski and Snowboard Club Vail Redevelopment, 598 Vail Valley Drive
Construction activity is contained within the construction fenced area. This is a redevelopment of the Ski and Snowboard Vail site to include a private and public club and multi-family residential dwelling units. The bike path on the south side of the project is currently closed; it scheduled to reopen by the end of November 2018, asphalt paving will not be completed until spring of 2019. Completion date is early winter 2018. General contractor is Viele and Company, David Viele, 970-476-3082. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Hill Building, 254 Bridge Street
Construction deliveries will continue to occur on Bridge Street for the project between 7 and 8:30 a.m. Oversize deliveries for the project on Upper Bridge Street will be coned off to keep pedestrians safe while material is delivered. Pedestrian traffic control will be provided. This is a major remodel of the building. Use of additional right-of-way requires submittal and approval of a public way permit. The trash dumpster will be staged on-site and fenced off. The project completion date is scheduled for spring of 2019. Contractor is Olson & Sons Construction Inc., Tim Olson, 970-390-7303. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Vail Health Hospital East Enabling Work                                                               
Site shoring and excavation of dirt is ongoing. All construction traffic will enter and exit on West Meadow Drive, which will see an increase in oversize vehicle traffic. Please exercise caution along South Frontage Road and West Meadow Drive near the construction project. Phase II of the Master Facility Plan includes the tear-down and replacement of the current east wing administration building and garage, replacing it with a new garage and new building to house new emergency and imaging departments, as well as a new lobby, central plant, tenant space and material management department. All hospital services will remain open and fully functional throughout the construction. To access the Emergency Department, use West Meadow Drive. Hospital patients and visitors should park in the hospital parking lot on South Frontage Road West. Patients and guests of the Medical Professional Building (US Bank) should park in the lot accessible by West Meadow Drive. Please see map. Contractor is G.E. Johnson Construction Company, Christian Earl, 307-203-9242.Town of Vail contact is Leonard Sandoval, 970-390-4677.

Row House Unit 8, 303 Gore Creek Drive
Work consists of an interior and exterior remodel; work will be contained within property boundaries and construction fencing. Project completion is scheduled for fall of 2018. Contractor is Cuccia Construction, Guy Cuccia, 970-471-6456. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Row House Units 9 & 10, 303 Gore Creek Drive
Single lane closures are scheduled for deliveries and concrete pours throughout the summer, fall and winter months; traffic control will be provided. Construction activity will be contained within property boundaries and construction fencing. Project consists of an interior and exterior remodel. Contractor is Beck Building, Gary Kendall, 720-202-5645. Town of Vail Contact is Leonard Sandoval, 970-390-4677.

Row House Units 11 & 12, 303 Gore Creek Drive
Single lane closures are scheduled for deliveries and concrete pours throughout the summer, fall and winter months; traffic control will be provided, Project consists of an interior/exterior remodel and addition. Project completion date has yet TBD. Contractor is SRE Building Associates, Casey Brune, 970-376-5568. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Lionshead

Battle Mountain/Lazier Parking Garage, 534 East Lionshead Cr.
Project is complete; the eastern lot is under design for a future project which is scheduled for Spring of 2019. General contractor is Meadow Mountain Homes, Sean McGinley, 970-926-2824 (office); Town of Vail contact is Leonard Sandoval, 970-390-4677.

Lionsquare Lodge South Interior Renovation, 660 Lionshead Place
Storm drain work is scheduled to occur in the next couple of weeks, it will affect the heated sidewalk on Lionshead Place. Work should be completed within 5 days. Remaining work is currently contained within the site boundaries. The project includes interior upgrades to the existing conference room, including new celling finishes, room dividers, lighting and interior trim and parking lot improvements. Contractor is R.A. Nelson & Associates Inc., Matt Anderson. Town of Vail Contact is Leonard Sandoval, 970-390-4677.

Vail Marriott Interior Renovation, 715 West Lionshead Circle
The project includes renovation of existing ballrooms, meeting rooms and associated corridors and the renovation of existing guest rooms and corridors. Construction start date was March 26 with a completion date of mid-September. Contractor is Digney York Associates LLC, Don Glorius, 703-790-5281. Town of Vail contact is Leonard Sandoval, 970-390-4677.

Outlying

West Vail Sewer Main Improvements – West Vail South Frontage Road

Eagle River Water & Sanitation District, in cooperation with the Town of Vail, is installing new sewer main within the South Frontage Road West corridor. The project is critical to increase sewer main capacity in the West Vail area so ERWSD can accommodate peak sewer flows in the future. The District partnered with town of Vail to install electrical conduits along S. Frontage Road in order to allow for the removal of the existing overhead power lines. The district and town cooperated to complete both improvements and reduce overall impacts to the public. Phase 1 of the project was in S. Frontage Road West, between Stephens Park and Elliot Road in Intermountain, and Phase 2 is located east of the Exit 173 roundabout, on S. Frontage Road by Conoco. Underground work and system testing in both areas is complete. Milling, paving, and temporary striping is scheduled for Sept. 10-12 throughout the project area; once complete, S. Frontage Rd. will fully reopen and the ECO Transit bus stop will be at its regular location on S. Frontage Rd. Permanent striping will occur in about three weeks. Travelers should use caution in the area as the shoulder of the eastbound lane will be used for construction staging while the project continues in an easement on the Casa del Sol Condominiums property. The intersection of W. Gore Creek Dr. with S. Frontage Rd. W. will close Sept. 24 to connect newly installed sewer main to existing sewer main. The west end of W. Gore Creek Dr., from the bridge to S. Frontage Rd. W., will be closed for two weeks. Access to W. Gore Creek Dr. will only be available from the east, via Matterhorn Circle. Motorists, bicycles, and pedestrians are advised to use the east end of W. Gore Creek Dr. Town of Vail will move bus service to S. Frontage Rd. during that time period. The contractor is Western Pipeway. ERWSD contact is Jeffrey Schneider, 970-445-7941.

Sewer Main Improvements, Bridge Road and Recreation Path in East Vail
The Eagle River Water & Sanitation District, in cooperation with the town of Vail, installed new sewer main and manholes along Bridge Road, north of Gore Creek, and along the recreation path west of Bridge Road to near the I-70 East Vail interchange. The recreation path will be reopened with minor construction work occurring on the shoulder. Sewer main installation is complete and new main is now connected to existing main. Seeding and final closeout activities will occur this week. Eagle River Water & Sanitation District contact is Melissa Marts, 970-471-1329. Town of Vail contact is Chad Salli, 970-479-2169.

I-70 East Vail Water Quality Improvements
The Town of Vail has contracted with United Companies to install water quality improvements at the East Vail interchange and two additional sites on I-70 near mile marker 182 to treat storm water runoff. Work under the I-70 bridges has been completed. Work at the East Vail interchange is near completion, landscaping will follow into the fall of 2018 with completion in the spring of 2019. This project is in partnership with the Colorado Department of Transportation which awarded the town a grant to pay for 80 percent of the construction costs. Town of Vail contact is Chad Salli, 970-479-2169.

Red Sandstone School Renovation, 551 North Frontage Road
The project includes the complete renovation of Red Sandstone Elementary School. Work includes removing the existing exterior finish material and installing new IECC compliant insulation and new exterior finishes, rearranging the existing school program and classrooms to allow for larger classrooms (to meet the current Eagle County School District standards). The new two-story addition along the south façade of the building will create a cafeteria, serving line, and secure vestibule all of which the school does not currently have. The second level of the addition will house the new library expanding the space to transform the library into a media center space as well. Demo and construction is underway, completion is scheduled for mid February 2019. Contractor is Haselden Construction, Justin Fahnestock, 303-549-8589.
 
Red Sandstone Elementary School Parking Garage, 551 North Frontage Road West
Pre-cast concrete is underway; The 350 ton crane is on site to install the pre-cast concrete for the parking garage. Work within the CDOT right of way is ongoing, work includes new steps to the pedestrian overpass bridge, parking lot and bike path improvements. Completion of this work is early October 2018. Excavation, shoring and removal of dirt are ongoing. Access to the school and the gymnastics center will be maintained as a clear zone. The bus stop is open west bound only. This project has a completion date of Nov. 15, 2018. The Town of Vail and Eagle County Schools are jointly constructing a four-level, 160 space parking structure on the current Red Sandstone School site. The work will include extensive site work to establish a loop road around the parking structure to allow access to each level while at the same time provide a one-way loop road for school drop-off and pick up. Contractor is Haselden Construction, Justin Fahnestock, 303-549-8589. Town of Vail contact is Chad Salli, 970-479-2169.

Solar Vail Apartments, 501 N. Frontage Road West
Removal of the remaining structure is complete, site shoring, excavation and dirt removal is underway. The existing employee housing located just east of the Vail Gymnastics Center will be demolished and replaced with a 4-story, 65-unit rental housing development for Sonnenalp Resorts. Occupancy is anticipated by October 2019. Contractor is RA Nelson, Justin Pronga, 970-471-0509. Town of Vail Contact is Leonard Sandoval 970-390-4677.


Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for the email updates, visit Vailgov.com and click on “Town Services,” then “Vail Mail Newsletter.” On this page you can sign up for “Construction Updates” as well as other useful Town of Vail newsletters.

 

 