Weekly Construction Update, Jan. 18

  • 15 January 2021

Primary Contact: Leonard Sandoval, Town of Vail Construction Area Coordinator  
970-390-4677 or 970-479-2198; lsandoval@vailgov.com 

Remote Video Inspections Now Available

Due to the ever-changing landscape and continuing challenges due to the pandemic, the Town of Vail is now piloting a Remote Video Inspection program. The general details and requirements for participation are located here. To check your eligibility for participation or for any questions regarding the program, contact CJ Jareckichief building official, at cjarecki@vailgov.com.   
 

Holidays and Special Events (No Work Days) 

Martin Luther King, January 16-18 
Presidents Weekend, February 13-15 

2021 Construction On Street Parking and Construction Staging 

No on street parking or construction staging is allowed during the winter months to April 15All contractors must remove or relocate any construction related items from the town right of way, 10 ft. away from the edge of asphalt. Contractors, please revisit erosion control and construction fencing and make any necessary repairs. Paid parking in the Vail Village and Lionshead Village parking structures coincides with ski season operations. 

Construction Update Meetings 

The construction meetings have been canceled until further notice. Contractors working in the areas of the Vail Village and Lionhead core areas will continue to communicate to the Public Works Department, providing updates and coordinating projects as it relates to construction activity within the right of way. For more information, contact Leonard Sandoval, 970-390-4677.  

COVID-19 Related Announcements 

Vail Transit is operational with the modified winter schedule; face masks are required for drivers and all passengers and capacity is being limited to 20 riders max. Town of Vail offices are open for in-person services by appointment. Please conduct as much business online or by phone. For an update on Town of Vail plan review, permits, building inspections and other services, visit www.vailgov.com. For construction safety information, check here.   

Online Citizen Portal 

Customers of the Community Development Department have access to a 24/7 online citizen portal to submit applications for contractor registration and various construction-related permits. The portal, at http://vail.onlinegovt.com/ also accepts planning applications for review by the Design Review Board and Planning and Environmental Commission. In addition, residents can access the citizen portal to submit a code enforcement request or check to see the status of any permit activity in their neighborhood. To view frequently asked questions, visit http://www.vailgov.com/online-services.  


Email Notification Service for Contractors and Consultants 

Sign up to receive automatic email notifications when new Town of Vail Bids or RFPs are released. Look for the RFPs, Bids and Notices tab at www.vailgov.com.  


Here’s a recap of the various construction projects currently ongoing in Vail.   

Vail Village

 La Taberna Iberica Patio, 100 E. Meadow Drive Unit 15 
Includes excavation and construction for new site wall and foundation stem walls. The purpose of the construction is to create a new patio dining areaConstruction fencing has been erected to enclose the perimeter of the work area. Project start date was May 18; completion of work is late January 2021. Contractor is Rocky Mountain Construction Group, Jonny Cohen, 970-471-9258. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

Xcel Energy, Mill Creek Circle  
Work is completedFull mill and asphalt overlay is scheduled for spring 2021. Xcel Energy has contracted with Sitewise Corp to install a new main gas line between the properties of 304 Mill Creek and 345 Mill Creek Circle. Contractor is Sitewise Corp, Jarrett Schaub, 303-430-1414; Town of Vail contact is Leonard Sandoval, 970-390-4677. 

Mountain View Residence Phase II, 434 South Frontage Road East   
All construction activity is taking place behind the construction fence for the winter months. Sidewalk improvements within the right of way are complete for the fall season. Remaining improvements will be completed in the spring/summer of 2021. Work consists of a new heated walkwayinterior and exterior framing, plumbing and fire sprinkler installation. The north side of the parking garage within the construction fence area is the staging area for trucks and material deliveries. General contractor is Shaw Builders LLC. Jim Heid, 970-904-5669. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

Vail Health Master Facility Plan, 180 S. Frontage Road   
Vail Health has received a TCO (Temporary Certificate of Occupancy). The new main entrance to the hospital is now open, which is located along the South Frontage Road across the street from the Vail Municipal Building. Temporary signage has been installed at the Main Vail exit, south roundaboutdirecting vehicle traffic to the Vail Health facility. Hospital patients and visitors should now park in the new parking structure. Phase II of the Master Facility Plan included the tear-down and replacement of the current east wing administration building and garage, replacing it with a new parking garage and hospital building to house new emergency and imaging departments, as well as a new lobby, central plant, tenant space and material management department. Patients and guests of the Medical Professional Building should park (valet parking available, 8 a.m. to 4 p.m.) in the underground parking lot of the Medical Professional Building. Contractor is G.E. Johnson Construction Company, Travis ClemTown of Vail contact is Leonard Sandoval, 970-390-4677.  

Row House Units 11, 303 Gore Creek Drive  
Single lane closures are scheduled for deliveries throughout the fall and winter months; pending public way permit approval. Traffic control will be provided. Project consists of an interior/exterior remodel and addition. Project completion date has yet TBD. Contractor is SRE Building Associates, Casey Brune, 970-376-5568. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

Lionshead 

There are no major construction projects in Lionshead 

Outlying 

Xcel Energy, Bighorn Road  
Work is completed for the winter months. Final bike path asphalt repairs (mill and asphaloverlay) will occur in the spring of 2021. Contractor is Sitewise Corp., Jarrett Schaub, 303-430-1414. Town of Vail contact is Leonard Sandoval, 970-390-4677. 

Xcel Energy, Juniper Lane  
This project will be delayed until spring 2021. Xcel Energy has contracted with Sitewise Corp. to excavate and install a new gas main on Juniper Lane from the intersection of Meadow Drive/Juniper Lane to the intersection of Main Gore Drive/Juniper Lane. Contractor is Sitewise Corp, Jarrett Schaub, 303-430-1414; Town of Vail contact is Leonard Sandoval, 970-390-4677. 


Do you know of others who would be interested in receiving construction updates from the Town of Vail? To sign up for the email updates, visit Vailgov.com and click on “Town Services,” then “Vail Mail Newsletter.” On this page you can sign up for “Construction Updates” as well as other useful Town of Vail newsletters.  

 